Summary
Key Features
- Overall Capacity : 6 MMTPA
- Major Processing Units: CDU/VDU, NHT, CCR, ISOM, HCU, DHDT, DCU, CRU, HGU, LPG TREATING UNIT, SRU, Utilities & Offsites, Cross Country Pipeline, Crude Oil Terminal and Marine facilities
- Total Project Cost (in USD): USD 2.5 billion
- Schedule : 48 Months
Challenges
Bina Refinery
Project
Process
- Water source, River Betwa is located 8 KM from site. Weir was built across the river to create pondage of water and intake well with pumps was constructed mid-stream of the river.
- 935 Km long cross country pipeline to transport crude from Gujarat to MP.
- Petcoke based captive co-generation power plant built first time in an Indian Refinery to utilise Petcoke produced in DCU.
- Integrated Hydrocracker and DHDT unit built for first time in India.
- Foundation field bus technology used across the Refinery.
- Designed as a Zero effluent Refinery.
Achievements
HSE: No loss time accident
Awards
- Construction Industry Development Council (CIDC) Vishwakarma Award-2011 for Best Project in Oil & Gas category
- Project Management Institute (PMI) Award-2010